Tags
bridges, engineering, Gunpowder Falls, HISTORY, Public Works, susquehanna, tunnel, water history
In my previous post I talked about the Fullerton Filtration Plant and the problems with it becoming a reality. Below are some photographs from the pre-planning stages of the Fullerton Plant. 1964 – when engineers were still able to look ahead and plan for the future.
Contractors moving the Fullerton connection into place.
Connecting the ‘Y’ branch to the Susquehanna pipe line. The Susquehanna pipe line was known as the “Big Inch” being 108 inches in diameter. This connection dropped it down to 96 inches. The metal mesh is for pouring concrete around the pipe line to hold it in place.
Capping off the end for future contractors to be able to connect the Fullerton Plant, if and when…
Just up the road is the Big Gunpowder Falls (Loch Raven and Prettyboy dams are on this river, way upstream). The Big Inch went under the Falls at this point. To the left is Interstate 95, back then known as the North-East Expressway.