I was asked last week about a new filtration plant to be built at Fullerton, Baltimore County. Here is what I found:

1955 – Dr. John C. Geyer, Consultant for Baltimore City, and Mr. Jerome B. Wolff, Consultant for Baltimore County Metropolitan District, having concluded their study of the entire distribution system submitted their report on July 1, 1955. According to the Fullerton Reservoir Study Preliminary Design Report of 2000, the 1955 Geyer-Wolff Report recommended purchasing a tract of land in the Fullerton area – which the City of Baltimore did purchase – for the future construction of a water treatment facility, a water storage reservoir, and a water pumping station.
1962 – On November 23, the sinking of shafts for the Fullerton Tunnel began. Both shafts were completed but no Fullerton Tunnel had been driven to date. (Project, Section #6 Susquehanna conduit) Tunnel completed for Fullerton in 1963.
1993 – Design of the Fullerton Pumping Station. PS completed in 1999
1997 – Design for Fullerton Reservoir
1999 – The design of the reservoir would be based on receiving 120 MGD from the future filtration plant. The study showed that the system could not support a 160 MGD reservoir. The reservoir was to be designed to elevation 226. The design proposed two reservoirs to be built, each with baffles. The reservoirs would have separate influent and effluent chlorination provided. As of December, 1999, the study was 75% completed. (Same report info in 2003)
2006 – A two year study began on May 2006. Approval was given to construct a pilot plant to test the operation of the membrane technology.
2007 – Reason contract on-hold is due to financial constraints caused by the artificial 9% rate cap; studies on the construction of the Fullerton Filtration Plant; continuation of the hypochlorite conversion project; and, the federal requirement to cover finished water reservoirs.
2008 – The draft of the Project Development Report for Fullerton, dated May 2008, was submitted for review and returned with comments. There were 4 alternatives in the review. As of October no method has been selected from the alternatives selected. Due to the economy at the time, the cost for each of these alternatives was in excess of $400M. The study had been extended to March 28, 2009. The cost proposal, received on June 23, was not accepted. The cost allocations to all concerned is still being worked on.
2009 – The Fullerton Filtration Plant construction had been delayed until 2017. If this project is ever resurrected, a new consultant agreement will need to be executed.
2010 – The contract for designing the facility could not be advertised until the cost allocation had been agreed upon.
2011 – The contract for designing the facility (Treatment Plant) could not be advertised until the cost allocation had been agreed upon. Also this year, repairs to the Montebello filters were initiated – “The filters were needed to be kept in service for another decade until the Fullerton Facility had been built and the new Montebello Facility was released for construction.” (New Montebello Filters never happened – Band-Aid after Band-Aid)
2012 – Fullerton Water Filtration Study: The contract for designing the facility could not be advertised until the cost allocation had been agreed upon. The Fullerton construction had been delayed originally until 2017. The Fullerton Reservoir would need to be constructed first. The design contract was expected to be released for bid in 2013 under the Fiscal Year 2014 budget, with a design completion date set for 2016. Construction was expected to begin in 2017 and was to be completed by 2021.
2014 – The Office of Environmental Compliance and Laboratory Services began gathering information in preparation of the contracts’ future pending design release. In 5-years the DPW of Baltimore expected the Fullerton Filtration Plant to be built and online thus clearing the path to fully renovate one of the two Plants at Montebello and shutting down operation of the second Montebello Plant.

Readers Digest version: The 100 year old Montebello Filters keeps being patched up while the City and Counties fight over who is going to pay what, for a new filter treatment plant at Fullerton. Status of Fullerton – it will be built, sometime in the future.